By Railroad News on Tuesday, 11 September 2018
Category: Progressive Railroading

BART preps for earthquake safety at Fruitvale Station

Rail News Home Safety 9/11/2018 Rail News: Safety

To help the infrastructure withstand earthquake damage, BART is retrofitting fixtures in and around the station.Photo – Bay Area Rapid Transit

Bay Area Rapid Transit (BART) this month plans to perform seismic retrofit construction work inside its Fruitvale Station in Oakland, California.

Workers will retrofit columns and fixtures in and around the station to help the infrastructure better withstand earthquake damage.

As part of the pre-construction activities, a worker used a scissor lift to scan the structures in preparation for the retrofit work.

Crews also are strengthening each column that holds up the elevated BART trackway under the alignment.

The work inside the concourse is expected to last four to six months, agency officials said in a press release.

BART's $1.3 billion earthquake safety program calls for upgrading vulnerable segments of the agency's original rail system. Portions with the highest traffic will be upgraded to ensure they can return to operation shortly after a major earthquake.

Within the next 30 years, there is a "high probability" of one or more major earthquakes hitting the San Francisco Bay Area, according to a U.S. Geological Survey analysis.

Contact Progressive Railroading editorial staff.

More News from 9/11/2018


Original link