Veolia Transportation Maintenance and Infrastructure (VTMI, Inc.) has chosen Dewberry to perform services under its design-build contract for new rail connections between the Florida East Coast (FEC) railway and the South Florida Rail Corridor (SFRC) in West Palm Beach and Miami, Fla.
Dewberry will perform surveys and provide grading, drainage and track engineering design work for the project.
TNW Logistic Services, LLC, is partnering with the Perry County Port Authority (PCPA) to expand economic development opportunities in the Tell City River Port area, which is located on the Ohio River in southern Indiana. The venture marks TNW's initial entry into Indiana.
TNW cites the area's location, land availability and existing train and port operations as an ideal place for a world-class transportation, operations and storage hub that connects the port to the Norfolk Southern at Lincoln City, Ind. TNW says the intermodal complex creates a natural gateway to locations throughout the United States for products and materials from ports on the Ohio River, the Great Lakes and the Gulf of Mexico.
4/11/2017
Rail News: Norfolk Southern Railway
4/11/2017
Rail News: Norfolk Southern Railway
Union Pacific (UP) is investing approximately $77.1 million in Oregon infrastructure this year to increase safety and efficiency.
Three East Coast senators are highlighting the need for increased funding of Amtrak following two derailments at New York Penn Station.
Rep. Mike Quigley (D-IL-5) joined representatives from the Illinois rail industry for a public policy discussion and a tour of Industry-Railway Suppliers, Inc., (IRS) at its Elmhurst, Ill., headquarters on April 10.
Rep. Quigley is a member of the U.S. House Appropriations Subcommittee on Transportation, Housing and Urban Development, and Related Agencies (THUD) and industry stakeholders discussed the importance of the shortline tax credit and the effort to make it permanent through the Building Rail Access for customers and the Economy (BRACE) Act. Additionally, the discussion touched on opposing any effort to increase truck sizes and weights, as well as opposing any federal reregulation of the industry.
4/11/2017
Rail News: Passenger Rail
2017 MOW capital budget: $73 million
2016 MOW capital budget: $50 million
Reasons for increase: About $21 million is budgeted for improvements to West of Hudson undergrade bridges, including the Moodna and Woodbury viaducts.
Rail: Replace, rehab or install 15 miles of rail.
Significant rail/track project: Begin undercutting on the inner New Haven Line, $500,000.
Ties: Install 44,200 wood ties.
Switches/turnouts/interlockings: Install 5 turnouts and 3 double-slip switches in Grand Central terminal, and 10 crossovers, 5 turnouts, 1 double-slip switch and 1 diamond along the right of way.
Bridge work: Perform steel and concrete repairs to 13 undergrade bridges; install new timber decks on 17 undergrade bridges; and install steel headblock ties, timber decks and new miter rails at 3 moveable bridges, 1 track each.
Stations/facilities: Paint, install benches and upgrade station lighting to LED lights at Tuckahoe and Fleetwood stations.
Electrical/mechanical work: Perform power system improvements around the territory, $35 million; Connecticut DOT continues to replace the original catenary system on the New Haven Line and should complete the work in 2018.
2017 MOW capital budget: $58 million
2016 MOW capital budget: $58 million
Rail: Replace, rehab or install 6 miles of rail.
Significant rail/track project: Twin Peaks Tunnel track replacement, 4 miles, $58 million; and M-Ocean View track replacement at 19th Avenue and Roosmoor Drive, 1.2 miles, $9.5 million. Both projects are within the limits of the city and county of San Francisco.
Ties: Install 11,000 wood and 11,000 composite ties during various track projects.
Switches/turnouts/interlockings: Multi-year Green Light Center rail replacement project (costing $39 million) includes the replacement of 57 turnouts and several interlockings in addition to the replacement of tracks; and the Twin Peaks Tunnel track replacement project (costing $58 million) includes the replacement of 8 turnouts and several interlockings in addition to the replacement of tracks.
Stations/facilities: Muni Metro East five-track extension project, phase 2, includes the construction of new track, overhead catenary and a traction power system, $17 million.
Electrical/mechanical work: Muni Metro Subway electrical and mechanical improvements program, $1.5 million.
2017 MOW budget: $8,992,260
2016 MOW budget: $5,624,965
Reason for increase: The 2017 budget includes $3 million in TIGER 7 funding.
Rail: Replace or install 5 track miles with 80-foot, 115-pound bolted rail.
Major rail project: (TIGER 7-funded project) Install 30,000 feet of rail, 52,000 ties, 32 turnouts and 17,000 tons of ballast, and surface 115 miles. Work to be spread over 2017 and 2018, with $3 million in federal funding each of those years.
Grinding/surfacing: Surface 90 miles.
Ties: Install 40,000 wood ties.
Ballast: Install 23,000 tons.
Bridge work: Repairs to culverts and bridges at various locations, $400,000.
Facilities: Reopen 7,000-foot passing track at Birchton, Quebec, includes turnouts, ties and ballast.
MOW equipment or purchase or lease: Lease 3 crew trucks and 1 boom material handling truck.
2017 MOW budget: $8 million
2016 MOW budget: $5 million
Rail: Replace or install 30,000 linear feet with new 141- and 136-pound CWR.
Sidings: Build 4,000-foot siding in Mohrsville, Pa.; 4,000-foot siding in Jim Thorpe, Pa.; and 3,000-foot siding in Hazelton, Pa.
Grinding/surfacing: Surface more than 60 miles.
Ties: Install 15,000 wood ties.
Ballast: Install 15,000 tons.
Bridge work: Plan to start construction on a new bridge over the Lehigh River in May.
Facilities: Build new shop facility at Port Clinton to work on MOW equipment and trucks, and construct a passenger station/transload facility in Reading, Pa.
MOW equipment or purchase or lease: Spiker and brush cutter.
2017 MOW budget: $765 million
2016 MOW budget: $764 million
Reason for slight budget increase: “CSX continuously reviews its investments in maintenance and infrastructure upgrades to ensure the railroad continues to deliver safe, reliable service for customers.”
Rail: Replace or install 470 track miles, all CWR.
Double track: Expect to spend $200 million to $250 million on line capacity improvements across the network, in addition to supporting continued investment in Chicago CREATE projects.
Other track construction: Build 49 miles of new track and install/construct 84 turnouts in Alabama, Indiana, Kentucky, North and South Carolina, New York, Tennessee and Virginia in 2017 (includes RF&P Subdivision projects in Virginia, and potential start of Howard Street Tunnel and Camden Street sewer relocation in Baltimore).*
Grinding/surfacing: Grind 18,000 pass miles, surface 5,000 miles.
Ties: Replace or install 2.8 million ties; about 2,700 will be concrete, with the remainder wood or composite ties.
Ballast: Install 2.6 million tons.
Bridge work: Improvement capital program is budgeted at $85 million and includes replacing and upgrading timber, concrete and steel bridges; replacing steel-pin trusses; improving decks; replacing culverts and improving other drainage; and enhancing the reliability of movable bridges.
Facilities: Total budget of $7 million for yard electrical distribution upgrades ($2.8 million), HVAC replacements ($1 million), roof replacements ($1 million), upgrades to existing buildings ($900,000), lease renewals ($500,000) and other projects ($800,000).
MOW equipment to purchase or lease: 5 tampers, 3 tamping carts and several pieces of new equipment that will automate some tasks and perform multiple functions.
* Information from CSX’s presentation Jan. 11 at the NRC’s 2017 conference
2017 MOW budget: $721 million (in Canadian dollars)
2016 MOW budget: $714 million (in Canadian dollars)
Rail: Replace or install 454 miles with 115- and 136-pound CWR.
Grinding/surfacing: Production grind 13,625 miles, complete 14,500 switch and crossing grinder events.
Ties: Replace or install 1.25 million wood and 7,000 concrete ties.
Bridge work: Plan replacement, rehab and upgrade projects at 99 sites, $42 million.
MOW equipment to purchase or lease: Plan equipment purchases totaling $44 million in 2017.